Project Infrastructure

Mine facilities being developed by the Company

ETHIOPOTASH is supported by the very best of technical experts, leaders in their fields, to design its mining operations (solution mining, evaporation ponds and brackish wells), freshwater wells, process plant, supporting infrastructure and port terminal

Unlocking the Potential of the Dallol Potash Project

0 MT

Annual Production

Phase 1 targets 300,000 metric tons per annum (mtpa) of SOP, with Phase 2 expansion doubling capacity to 600,000 mtpa.
0 +

Years of Resource Potential

Estimated mine life of 30 years at full production capacity.
0 Sustainable

Solution Mining

Uses water from underground aquifers for potash recovery, ensuring minimal environmental impact.

Strategic Agreements in Place

🔹 Land lease & port services agreements secured.
🔹 Government-approved transition of ownership in 2023.

Proven Technical & Economic Viability

📊 Feasibility study confirms strong technical & economic merits, paving the way for future development.

Advancing Towards FEED Stage

🏗 Pre-FEED studies (LiDAR surveys, geotechnical assessments, environmental evaluations) completed.

Project Execution Plan

Specifications approved

Updated CAPEX

Solution mining
Ponds
Process plant
Water wells
Terminal
Other
Project Infrastructure
42 caverns of 30m radius to be initiated and replaced annually
55 ponds representing a combined surface of 5.5km2
A wet plant and a dry plant to treat product from crushing to load-out
21 wells to be drilled, located in a 5km radius around the Dallol site
Storage area for 75,000 MT with ability to load ship at 1,200 MT/h
Permanent workers’ camp Administration building
Design Advisor

Major project infrastructure developed by external stakeholders

Overview of key third party infrastructure investments tailored for the projects needs

Power lines

Lowland roads

Port